S
Stuart @ Childrens Hospital
Critical Chain is a variation of Critical Path; it adds resource leveling to
the critical path consideration. Tasks in a chain become critical if task
duration or resouce availability changes would cause a delay in the project
completion.
When I resource level in project, the tasks do not show up in the critical
path (view: Detail Gant) unless I set the task precedence. For a task group
(using only one resource each task) that should be on the critical path,
leveling does schedule the tasks to occur sequentially, but the group does
not show up as a critical path. I would like tot Detail Gantt to show this
is the critical path (or critical chain!).
Thank you
the critical path consideration. Tasks in a chain become critical if task
duration or resouce availability changes would cause a delay in the project
completion.
When I resource level in project, the tasks do not show up in the critical
path (view: Detail Gant) unless I set the task precedence. For a task group
(using only one resource each task) that should be on the critical path,
leveling does schedule the tasks to occur sequentially, but the group does
not show up as a critical path. I would like tot Detail Gantt to show this
is the critical path (or critical chain!).
Thank you