R
Robin Roe
Hi
In our organisation we have tasks that run the entire lenght of a project
such as Project Management. The duration of these tasks depend totally on the
duration of the entire project so we have created a hammock tasks for the
likes of the Project Management task using strat project and finish project
milestones.
The problem is that because these tasks will never have any slack, they will
always show up on the critical path. Is there anyway of excluding these
tasks? Have tried making them slightly shorter but it's really not an ideal
solution.
We are currently usong 2003, but perhaps 2007 has a more suitable solution
for this? Primavera uses "Level of Effort" tasks to get around this.
Thanks for your help
In our organisation we have tasks that run the entire lenght of a project
such as Project Management. The duration of these tasks depend totally on the
duration of the entire project so we have created a hammock tasks for the
likes of the Project Management task using strat project and finish project
milestones.
The problem is that because these tasks will never have any slack, they will
always show up on the critical path. Is there anyway of excluding these
tasks? Have tried making them slightly shorter but it's really not an ideal
solution.
We are currently usong 2003, but perhaps 2007 has a more suitable solution
for this? Primavera uses "Level of Effort" tasks to get around this.
Thanks for your help