Vit --
In the future, please post your Project Server questions in the
microsoft.public.project.server newsgroup, as this newsgroup is dedicated to
the Microsoft Project desktop application only. To answer your question,
there is no difference betwee the Gantt Chart view and the Enterprise Gantt
Chart view IN APPEARANCE. They both look the same. However, here's the
difference:
1. The Gantt Chart view and Entry table are stored on the Global.mpt file
on your hard drive. You can either either the View and/or the Table as you
wish to personalize them.
2. The Enterprise Gantt Chart view and Enterprise Entry table are stored in
the Enterprise Global file. Only the Project Server administrator can edit
either the View and/or Table. Some organizations edit the Enterprise Gantt
Chart view to provide a single customized Gantt Chart view that looks the
same for everyone.
Hope this helps.