D
dgmoore
We have a master schedule (Prj2003) that includes certain milestones
that we would like to display in a number of "external" schedules.
These milestones are not predecessors of any tasks in those schedules,
and the external projects are not sub-projects of the master schedule.
Is there a way to link milestones from the master schedule to an
external schedule so that changes to those milestones would show up in
the external schedule?
Thanks
Dave
that we would like to display in a number of "external" schedules.
These milestones are not predecessors of any tasks in those schedules,
and the external projects are not sub-projects of the master schedule.
Is there a way to link milestones from the master schedule to an
external schedule so that changes to those milestones would show up in
the external schedule?
Thanks
Dave