Display Predecessor and Successor Tasks

Discussion in 'Project' started by Thomas Schuber, Sep 2, 2014.

  1. Thomas Schuber

    Thomas Schuber

    Joined:
    Sep 2, 2014
    Messages:
    1
    Likes Received:
    0
    Hi All,

    I used a VBA Macro from Rod Gill to display predecessors and successor tasks for a selected task.
    The macro runs fine if I use it only for single project files.
    It shows the pre- and successor tasks, and the task itself will be selected (highlighted).
    But when I want to display the pre- and successor tasks within a subproject file that is included in a master project file, it does no longer work as expected. The pre- and successor tasks are shown, but the task itself is not selected.
    The two very last VBA statements in the main function are:

    EditGoTo Tsk.ID
    SelectRow


    With EditGoTo Tsk.ID and SelectRow, the task for which I want to see the pre- and successors are selected (highlighted).
    EditGoTo Tsk.ID seems to fail if the task is located in a subproject included in a master project.
    I tried EditGoTo Tsk.UniqueID instead, but this also fails.

    Any idea how to fix this?

    Thanks,
    Thomas
     

    Attached Files:

    Thomas Schuber, Sep 2, 2014
    #1
    1. Advertisements

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments (here). After that, you can post your question and our members will help you out.