Hello,
I have been unable to display the baseline milestone dates on my gantt
chart. I added another Milestone line under the Format Bar Styles for my
baseline milestones and selected an appearance, Show for Milestone Tasks, Row
2 From Baseline Start to Baseline Finish. My current dates are the only
milestone dates that appear. Btw, the baseline milestone dates that I am
referring to are different dates...a year or so apart.