displaying baseline milestones on gantt

M

mikejw

Hello,

I have been unable to display the baseline milestone dates on my gantt
chart. I added another Milestone line under the Format Bar Styles for my
baseline milestones and selected an appearance, Show for Milestone Tasks, Row
2 From Baseline Start to Baseline Finish. My current dates are the only
milestone dates that appear. Btw, the baseline milestone dates that I am
referring to are different dates...a year or so apart.

Thanks for your help.
 
J

Jan De Messemaeker

Hi,

I don't completely understand what you mean by a year apart. Are these zero
duration milestone tasks? If yes, draw them from Basline2start to
Baseline2Start or from finish to finish.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 