Duration formula for Project Start to task Finish date

B

Berner

I have a contract requirement to deliver a product 60 days after the
start of the project. This task only takes two weeks to complete. I
would like make a customize Duration field that calculates this
duration from Project Start date to the Finish date of the task. What
formula would you suggest?
-Berner
 
C

Catfish Hunter

Try this: start1 = [start]-[text1] In text 1 type .125 (3/24) Let me know if
this helps.
 