G
Goose
Hello. I have a project plan that I am using 2 custom date fields. I want
to calculate the duration of these 2 date fields and I cannot seem to get the
actual duration, but I am able to get the variance using
ProjDateDiff([Date31,Date2]). I would think that this is a simple solution,
but I am not able to solve it. I also created a new date field (Date3)
(Date1 minus one day) ProjDateSub([Date1],1) and then used the same
ProjDateDiff([Date3],[Date2]) but that came up with the same variance as
before. Is there anyway to get the actual duration of 2 custom date fields?
to calculate the duration of these 2 date fields and I cannot seem to get the
actual duration, but I am able to get the variance using
ProjDateDiff([Date31,Date2]). I would think that this is a simple solution,
but I am not able to solve it. I also created a new date field (Date3)
(Date1 minus one day) ProjDateSub([Date1],1) and then used the same
ProjDateDiff([Date3],[Date2]) but that came up with the same variance as
before. Is there anyway to get the actual duration of 2 custom date fields?