J
James
I am wondering if it is possible in MS Project 2002 to set a duration time
like 4h that will not affect the Start and Finish dates. I have a resource
that will need 4h to complete a task but it can be completed anytime during a
1 week time span. So what I want is to put 4h? in the duration field and the
set the Start date to Mon 8/29/05 and the Finish date to Fri 9/2/05. Can
this be done?
like 4h that will not affect the Start and Finish dates. I have a resource
that will need 4h to complete a task but it can be completed anytime during a
1 week time span. So what I want is to put 4h? in the duration field and the
set the Start date to Mon 8/29/05 and the Finish date to Fri 9/2/05. Can
this be done?