I am in leveling gantt view and it says e day.  what does the e stand for?

I don't know officially what it stands for (evening and day?) but it
made my resources available 24 hours a day on the tasks that had the e
in front of my durations.
 
M

Mike Glen

Hi Té,

Welcome to this Microsoft Project newsgroup :)

The e stands for elapsed. Elapsed times ignore the working calendar times
and thus include nights and week ends.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 