Earned value (BCWP) showing as zero in chart

Discussion in 'Project' started by Connell Maskrey, Apr 1, 2015.

  1. Connell Maskrey

    Connell Maskrey

    Joined:
    Apr 1, 2015
    Messages:
    1
    Likes Received:
    0
    Hello. I am using physical% complete to calculate earned value each week (status date) and this calculating as expected o provide planned, earned and actual cost indicators, HOWEVER when I go to chart this the earned $ shows as zero??

    I am using MS Project Professional 2013, so also tried the file on MS Project Standard 2010 and noted that the physical % complete was not rolling up through summary tasks, hence it was not calculating earned value, even though it was working in the 2013 version. Is there some way that the physical % complete field has become corrupted or is there a settign I can check for this field?

    I assume my zero $ earned value in the chart is related to this issue ... ie shows in gantt/table views, however in converting to chart/excel it loses som functionality in the physical % complete field

    PLEASE HELP !
     
    Connell Maskrey, Apr 1, 2015
    #1
    1. Advertisements

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments (here). After that, you can post your question and our members will help you out.
Similar Threads
  1. Moiz Khan
    Replies:
    0
    Views:
    671
    Moiz Khan
    Aug 12, 2014
Loading...