D
Darlene
On some of my tasks in my master project file, I am getting this error
message when I try to format the task bar in the Gantt chart:
"The argument value is not valid. Verify that the value is spelled
correctly, and that it is of the type that this argument expects."
What does this mean? I have nothing misspelled and there are no constraints
set. The task is linked to its predecessor properly and the duration is set
at 2 weeks. Nothing seems out of the norm as I have other tasks that work
fine in the Gantt chart. This only occurs on some of the tasks and it is
happening on more than one subproject. I have tried to unlink and reinsert
the subproject after being sure they are saved as 2007 projects. I upgraded
recently from 2003 to 2007 Standard and am not using the Server or
Professional versions. Any ideas?
message when I try to format the task bar in the Gantt chart:
"The argument value is not valid. Verify that the value is spelled
correctly, and that it is of the type that this argument expects."
What does this mean? I have nothing misspelled and there are no constraints
set. The task is linked to its predecessor properly and the duration is set
at 2 weeks. Nothing seems out of the norm as I have other tasks that work
fine in the Gantt chart. This only occurs on some of the tasks and it is
happening on more than one subproject. I have tried to unlink and reinsert
the subproject after being sure they are saved as 2007 projects. I upgraded
recently from 2003 to 2007 Standard and am not using the Server or
Professional versions. Any ideas?