I have several hundred tasks with resources assigned. I can then review the
overallocations in the Resource Graph view. I now want to be able to exclude
certain tasks by setting a Flag (in Task fields) to yes so that the Resource
overallocations exclude the assignements on those tasks with the falg set to
Yes - is this possible?
 
J

JulieS

Hi Steve,

I don't *think* so, at least not that I am aware of. I did add the Flag
field to the resource usage view, set a few flags to "yes" and I was able to
create the filter to "hide" those assignments in the Resource Usage view.
However, even though the assignments are hidden, the Resource Graph is still
displaying the work for those assignments.

Sorry, maybe some one else has a clearer head than I.