S
Shawn
Project is not behaving the way I'm expecting it to I understand the Work
= Units x Duration formula. I thought I understood the different task types
and effort driven but I guess not.
I want to change the duration of a task and I want Project to change units
not work. I have the task as fixed duration and effort driven. So for
example, duration 5 days, 1 resource with work 20 hours (4 hours per day)
which makes units 50%. So, when I change duration to 10 days, I want Project
to keep the work at 20 hours and change the units to 25%. But instead,
Project keeps the units at 50% and changes the work to 40 hours. How do I
solve this problem?
= Units x Duration formula. I thought I understood the different task types
and effort driven but I guess not.
I want to change the duration of a task and I want Project to change units
not work. I have the task as fixed duration and effort driven. So for
example, duration 5 days, 1 resource with work 20 hours (4 hours per day)
which makes units 50%. So, when I change duration to 10 days, I want Project
to keep the work at 20 hours and change the units to 25%. But instead,
Project keeps the units at 50% and changes the work to 40 hours. How do I
solve this problem?