M
mcm
hi i just started working on project a few days ago and im still confused on
why my duration and start/finish dates keep changing. im working in gantt
chart and i need it to be calendar days so i changed it to 24 hours (not sure
if that is right). however when i enter a task that is 66 days, the start
date is correct but the finish date goes past the date i need it to end. so i
started reading about the fixed durations and fixed units thinking that had
something to do with it but im still confused.how do i need to go about this?
why my duration and start/finish dates keep changing. im working in gantt
chart and i need it to be calendar days so i changed it to 24 hours (not sure
if that is right). however when i enter a task that is 66 days, the start
date is correct but the finish date goes past the date i need it to end. so i
started reading about the fixed durations and fixed units thinking that had
something to do with it but im still confused.how do i need to go about this?