M
MyriamD
I have a task: Duration 2 D, effort Driven.
I assign 2 resources (A and B), who will work each at 100%, so each have 16
h Work, total work for the task is 32 h.
I take off resource B. because Effort Driven is turned on, the amount of
work for the task remains 32 h and resource A is assigned at 200%. So far OK.
When I now assign resource C to the task, the amount of work for the task
still remains 32 h (as I wish), but resource A is assigned at 133% with 21,33
h Work and resource C is assigned at 67% with 10,67 h Work.
I would like them both working at 100%, each 16 h. Wy is MS Project behaving
like this. I know I can avoid this by replacing B with C immediately, but
this is not an option, because tasks might be more complex and I don't know
in before when I will get this kind of problem and have to replace resources
immediately.
I have this problem with MS Project 2003 and 2007
I assign 2 resources (A and B), who will work each at 100%, so each have 16
h Work, total work for the task is 32 h.
I take off resource B. because Effort Driven is turned on, the amount of
work for the task remains 32 h and resource A is assigned at 200%. So far OK.
When I now assign resource C to the task, the amount of work for the task
still remains 32 h (as I wish), but resource A is assigned at 133% with 21,33
h Work and resource C is assigned at 67% with 10,67 h Work.
I would like them both working at 100%, each 16 h. Wy is MS Project behaving
like this. I know I can avoid this by replacing B with C immediately, but
this is not an option, because tasks might be more complex and I don't know
in before when I will get this kind of problem and have to replace resources
immediately.
I have this problem with MS Project 2003 and 2007