Fixed Units/effort driven vs Fixed Work: any difference in calcula

K

K Major

When a fixed units/effort driven task calculates...

and a fixed work (it requires effort driven) task calculates...

there doesn't appear to be any difference in the calculation results of
duration. Is there a difference in the calculation results? If so, what is
it? If not, why even have a fixed work task type?

I must be missing something.

Thanks.
 
J

Jan De Messemaeker

Hi K,

Change the duration.
With Fixed Units you will se Work change
With Fixed Work you see Units change.
HTH
 