A
Aren Cambre
I am using MS Project 2003.
I have a project with 4 tasks with no constraints. They are all "As
Soon As Possible" tasks. They all last 1 day, and the resource
assigned to them is assigned at 25% units. All of these tasks are 0%
complete.
All four of these tasks have begin and end dates on 6/16/03, the start
of my project. This should not be happening: task 1's FS predecessor's
finish date is 12/19/03, task 2's FS predecessor is task 1, task 3's
FS predecessor is task 2, and task 4's FS predecessor is task 3.
Tools-->Options-->Calculation-->Calculation mode is Automatic.
I am totally confounded. Everything I read says this should be
working.
Aren Cambre
Web Developer
Southern Methodist University
I have a project with 4 tasks with no constraints. They are all "As
Soon As Possible" tasks. They all last 1 day, and the resource
assigned to them is assigned at 25% units. All of these tasks are 0%
complete.
All four of these tasks have begin and end dates on 6/16/03, the start
of my project. This should not be happening: task 1's FS predecessor's
finish date is 12/19/03, task 2's FS predecessor is task 1, task 3's
FS predecessor is task 2, and task 4's FS predecessor is task 3.
Tools-->Options-->Calculation-->Calculation mode is Automatic.
I am totally confounded. Everything I read says this should be
working.
Aren Cambre
Web Developer
Southern Methodist University