R
Rooster
Hi,
I'm trying to set up a project in hours, so one working day is 7.5 hours.
9am to 12:30 then 13:30 to 17:30. I would expect 5 continuous days to be
37.5 hours and in the Gantt chart shown as 5 full days.
Tools options set to work entered in hours. When I go to Tools, Change
Working Time I choose options and then enter the above and press Set as
default. Go back a screen and when I choose use default it still has 08:00
to 12:00 then 13:00 to 17:00. Anybody know what's going on?
Any help greatly appreciated.
MS Project 2003
R
I'm trying to set up a project in hours, so one working day is 7.5 hours.
9am to 12:30 then 13:30 to 17:30. I would expect 5 continuous days to be
37.5 hours and in the Gantt chart shown as 5 full days.
Tools options set to work entered in hours. When I go to Tools, Change
Working Time I choose options and then enter the above and press Set as
default. Go back a screen and when I choose use default it still has 08:00
to 12:00 then 13:00 to 17:00. Anybody know what's going on?
Any help greatly appreciated.
MS Project 2003
R