Hans
Hi
I need to display task costs by month. My client requires cost forecasting
by month for the whole Financial Year to enable them to program cash flow.
Right now this is done manually in Excel, and when the project moves around,
we have to spend a day or so each month correcting the cash flow for the
future months. I would like to do this in Project so that when the timeline
is adjusted, the cash flow requirements move with it automatically.
Any help is most appreciated
BTW- I am working with Project 2007
I need to display task costs by month. My client requires cost forecasting
by month for the whole Financial Year to enable them to program cash flow.
Right now this is done manually in Excel, and when the project moves around,
we have to spend a day or so each month correcting the cash flow for the
future months. I would like to do this in Project so that when the timeline
is adjusted, the cash flow requirements move with it automatically.
Any help is most appreciated
BTW- I am working with Project 2007