HOW CAN I SHOW THE END DATE OF THE 5 TASKS ON THE SUMMARY LINE

S

Swilli

I am trying to show a gantt chart where on one of the summary lines I want to
just show the end dates (as milestones) at the summary line.
 
D

DavidC

Hi Swilli,

Unsure why you would want this but, you can set the format for each bar
individually. Right click on the bar, select Format bar style, then change
the components of the bar to reflect the view as you want it.

Hope this helps

Regards

DavidC
 
J

John

Swilli said:
I am trying to show a gantt chart where on one of the summary lines I want to
just show the end dates (as milestones) at the summary line.

Swill,
I assume you mean that you want to show the finish date of each
performance task, (i.e. subtask), as a milestone on the summary line.

Insert a milestone tied to the finish date of each performance task.
Select all those milestones and go to Project/Task Information/General
tab. Check the box to "Roll up Gantt bar to summary". Likewise, select
the summary and pull up the task information window. This time check the
option to "Hide task bar".

Hope this helps.
John
Project MVP
 