Swilli said:
I am trying to show a gantt chart where on one of the summary lines I want to
just show the end dates (as milestones) at the summary line.
Swill,
I assume you mean that you want to show the finish date of each
performance task, (i.e. subtask), as a milestone on the summary line.
Insert a milestone tied to the finish date of each performance task.
Select all those milestones and go to Project/Task Information/General
tab. Check the box to "Roll up Gantt bar to summary". Likewise, select
the summary and pull up the task information window. This time check the
option to "Hide task bar".
Hope this helps.
John