M
Mesha
Hi,
I'm fairly new to project and am in the process of creating a few small IT
project plans. I have a lot of tasks that require monitoring over a several
day period. A particular task may take 8 effort hours to complete, but will
take a resource 3 days to complete. I know how to show the 3 day duration,
but how can I show these effort hours at the same time?
I'm fairly new to project and am in the process of creating a few small IT
project plans. I have a lot of tasks that require monitoring over a several
day period. A particular task may take 8 effort hours to complete, but will
take a resource 3 days to complete. I know how to show the 3 day duration,
but how can I show these effort hours at the same time?