Alistair Bruce
In my plan I have ten tasks assigned to resources (some BAs and some Devs via
a resource group). Some tasks are Approved and some are Unapproved (Text 1
value). In the Resource Usage view, against a given Resource; it will show
Task A 4 hours, Task A2 4 hours, Task Unapproved 2 hours with the summary
value of 10 hours (the line against the resource).
I need to filter the Resource Usage view to show only the Approved Tasks (ie
Task A1 and A2) and show the summary value of 8 hours.
The issue with the Summary value is if I have a Combination view with a
Resource Graph in the bottom pane; it graphs against the Summary values and
not the filtered value. It shows the resource over allocated because it
includes the Unapproved task (10 hours).
a resource group). Some tasks are Approved and some are Unapproved (Text 1
value). In the Resource Usage view, against a given Resource; it will show
Task A 4 hours, Task A2 4 hours, Task Unapproved 2 hours with the summary
value of 10 hours (the line against the resource).
I need to filter the Resource Usage view to show only the Approved Tasks (ie
Task A1 and A2) and show the summary value of 8 hours.
The issue with the Summary value is if I have a Combination view with a
Resource Graph in the bottom pane; it graphs against the Summary values and
not the filtered value. It shows the resource over allocated because it
includes the Unapproved task (10 hours).