How do I insert a new task into an existing project?

J

Jerry Richgels

I completed a schedule then realized I needed to insert another task in the
middle of the task list. Project is not allowing me to do this even when I
remove all known links. Are there other restrictions I must remove, like
Summary Tasks?
 
P

Prj_Mngr

So putting your cursor on a row and pressing insert doesn't work? I am not
aware of any problems with the links or summary tasks that would stop you
doing this. Could the file be read only, or you don't have correct network
rights to it?
 
R

Rod Gill

Do you have the project sorted or filtered? make sure the filter All Tasks
is displayed (shortcut for that is F3) and that you are sorted by ID
(Project, Sort menu).

Links and summary tasks should have no effect.

Can you insert into a new schedule?
 