W
WestSeattleMike
Hi All,
I'm trying to have 3 resources work on 1 task, but start on different dates
due to another task they are working on. See the sample below and please help.
Task 1, taking 5 days, being worked on by resource A.
Task 2, taking 9 days, being worked on by resource B.
Task 3, taking 2 days, being worked on by resource C.
Resource A, B and C all start at the same time, so clearly C will finish
first, then A, then B.
Task 4 takes 45 days and I want each resource (C, A & B) to jump onto task 4
as soon as they finish their previous task and I want project to calculate
how long it will take if resource C starts after his 2 days of work, resource
A starts after his 5 days of work and resource B starts after his 9 days of
work.
How do I put multiple resources on one task with different start days?
Thanks,
-Mike
I'm trying to have 3 resources work on 1 task, but start on different dates
due to another task they are working on. See the sample below and please help.
Task 1, taking 5 days, being worked on by resource A.
Task 2, taking 9 days, being worked on by resource B.
Task 3, taking 2 days, being worked on by resource C.
Resource A, B and C all start at the same time, so clearly C will finish
first, then A, then B.
Task 4 takes 45 days and I want each resource (C, A & B) to jump onto task 4
as soon as they finish their previous task and I want project to calculate
how long it will take if resource C starts after his 2 days of work, resource
A starts after his 5 days of work and resource B starts after his 9 days of
work.
How do I put multiple resources on one task with different start days?
Thanks,
-Mike