Hi,

Any one how do i set reminder befor each task is even start. to remind me
let's say a week before the task needs to start.

Thanks
Ronen
 
G

Gérard Ducouret

Hello Ronen,

Are you using Project Server 2003 ?
If so, you'll find in the PWA page "Alert me about my tasks and status
report" the option :
Alert me x days before my tasks start.

Gérard Ducouret
 
R

Ronen

Hi Gerard,

Thanks for you answer. I'm using project standard 2003, if it's working on
it please advise what's DWA page?

Thank you again,

Ronen
 
G

Gérard Ducouret

Ronen,
Sorry, it doesn't work on Project Standard unless you write a VBA
procedure - not very easy ;-(
PWA stands for Project Web Access, which comes with Project Server.

Gérard Ducouret
 