1) create Tasks, describe them properly with verbs, order and group them
within a sensible WBS with headings etc.
2) estimate Durations, keep them short. if more Tasks, more detail are
needed to get short durations, them make them.
3) make predecessor links, kep it simple, stick to FS0 or FS>0
4) assign Resources. usually better to make a complete list of Resources,
with type, max units, costs per hour and per use before assigning.
5) if you don't want to assign resources (but you should), just assign Fixed
Costs to Tasks in the Gantt View, Costs Table.
6) assign Fixed Costs, if necessary, also even if Resources (with Costs) are
assigned.
DONE!
Then save a Baseline (TOOLS, TRACKING, SAVE BASELINE)
.... except for all of the other things to remember such as Calendars, Task
Type, Effort Driven, Date Constraints, Leveling, analysis, optimisation,
Tables, Views, Filters, Groups, Sorting, output as Gantt Chart prints,
export to EXCEL, built in reports etc.