I have a project with the following information. The actual duration on the
project summary line seems awfully low, which I believe may be driving the
low overall percent complete. But I don't know which field is driving the
calculation. Looking at the individual tasks, the actual duration should be
around 20 days.
% complete = 3%
Duration = 167 days
Actual duration = 5.23 days
start = 5/12/05
finish = 12/30/05
status date = 9/17/05
Where can I find information on how summary levels lines are calculated? Or
are they a composite of the tasks beneath?
project summary line seems awfully low, which I believe may be driving the
low overall percent complete. But I don't know which field is driving the
calculation. Looking at the individual tasks, the actual duration should be
around 20 days.
% complete = 3%
Duration = 167 days
Actual duration = 5.23 days
start = 5/12/05
finish = 12/30/05
status date = 9/17/05
Where can I find information on how summary levels lines are calculated? Or
are they a composite of the tasks beneath?