V
verossa
Morning All
I am looking at my MS Project > Task View > Earned Value Table and I have the following information
BCWS: £360
BCWP: £2,915.2
ACWP: £430
SV: -£684.7
CV: -£1394.7
EAC: £590
BAC: £400
VAC: -£190
This is sample to test the EVA in MS Project - it only has one 10 day task. I have deliberately created a variance between the 'actual work' and baseline schedules to view the effects. However, I confused (as usual). Isn't there a formula for calculating BCWP
Any information would be appreciated :-
TIA - Vers
I am looking at my MS Project > Task View > Earned Value Table and I have the following information
BCWS: £360
BCWP: £2,915.2
ACWP: £430
SV: -£684.7
CV: -£1394.7
EAC: £590
BAC: £400
VAC: -£190
This is sample to test the EVA in MS Project - it only has one 10 day task. I have deliberately created a variance between the 'actual work' and baseline schedules to view the effects. However, I confused (as usual). Isn't there a formula for calculating BCWP
Any information would be appreciated :-
TIA - Vers