How to assign quantity of resources?

G

Glenda Padilla

How do I assign quantity of resources of a determined group, assigned to
different tasks for resource leveling purpose.
 
S

Steve House [MVP]

Run that by us again, Glenda. Can you give us a little more detail of your
situation?
 
M

Mike Glen

Hi Glenda,

Welcome to this Microsoft Project newsgroup :)

As I understand you, you just assign the group by name and the number of
units you require. If you do that, you cannot then assign an individual on
another task - its the group or the individuals by name.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 