H
hhspiny
I have spent almost entire night searching for an answer. it seems that
when you add multiple resources to a task, project always split the
work between resource evenly, which causes unused resource over the
course.
take a very simple situation.
I have a task that takes 8 man-hours to finish. I can only work 6 hour
a day.
1. assign myself to the task, total will be 1 day plus 2 hours next
day.
to keep within the one day limit, I hire a helper, who demands payment,
therefore, I need to make his work time as little as possible. in
project
2. I add the helper to the project. hoping that I still work 6 hours a
I could, but only assign the extra 2 hours to the help. BUT, project
doesnot think so. project would split the 8 hours between me and the
helper. each gets 4 hours. I end up wasting 2 hours, paying extra 2
hours to the helper.
given the above is simple situation, and you can adjust manually. but
when many tasks and resources are involved. it is not possible to
adjust manually.
How to avoid such in project?
Another similar situation, that doesnot target cost but the duration
I have a task take 8 man-hours. I can work 4 hours a day. helper can
only work 1 hours a day.
1. assign myself to the task. takes 2 days.
2. add the helper to the task. project split evenly the work, I get 4
hours, the helper gets 4 hours. but since the helper works 1 hour a
day, it take 4 days to finish the project. wowo, what is the logic???
I have search in the past newsgroup discussion. but never saw anyone
answered such problem.
when you add multiple resources to a task, project always split the
work between resource evenly, which causes unused resource over the
course.
take a very simple situation.
I have a task that takes 8 man-hours to finish. I can only work 6 hour
a day.
1. assign myself to the task, total will be 1 day plus 2 hours next
day.
to keep within the one day limit, I hire a helper, who demands payment,
therefore, I need to make his work time as little as possible. in
project
2. I add the helper to the project. hoping that I still work 6 hours a
I could, but only assign the extra 2 hours to the help. BUT, project
doesnot think so. project would split the 8 hours between me and the
helper. each gets 4 hours. I end up wasting 2 hours, paying extra 2
hours to the helper.
given the above is simple situation, and you can adjust manually. but
when many tasks and resources are involved. it is not possible to
adjust manually.
How to avoid such in project?
Another similar situation, that doesnot target cost but the duration
I have a task take 8 man-hours. I can work 4 hours a day. helper can
only work 1 hours a day.
1. assign myself to the task. takes 2 days.
2. add the helper to the task. project split evenly the work, I get 4
hours, the helper gets 4 hours. but since the helper works 1 hour a
day, it take 4 days to finish the project. wowo, what is the logic???
I have search in the past newsgroup discussion. but never saw anyone
answered such problem.