Hi Mike, I would be glad to share my situation and receive a qualified
comment on it.
However, there's nothing strange in it: organisation has three types of
projects - for-profit (of course, they are the principal ones),
administrative (in terms of Microsoft Project - vacations, illnesses,
business trips, telephone calls, etc.), and private projects. For-profit and
administrative projects form organisation's project portfolio. It is for
them, that we track resource load, durations and budgets. And level resources
only within project portfolio.
Private projects are the privilege of some managers who are authorised to
open new projects by their own - usually these are the projects of local
development of departments, systems, work on new ideas, etc. - they are
internal and can use resources only when they are free or volunteer to work
on these projects overtime.
In some sense these projects are virtual ones because many of them are just
personal plans and are executed in the heads of those managers.
For these projects their managers often assign resources (mostly themselves)
with serious overload (frankly speaking, I don't understand why for other
work they enter for example 8 hours per day and for their project it could be
10-16 hours per day). However, they have the right to operate with resource
assignments and I must accept the situation as it is.
My task is to separate private plans from project portfolio. With resource
leveling, portfolio analyser and other things it's OK, but even if I filter
the projects in Resource or Task usage views, I see the indicators for
resource overload for all projects of the organisation.
That's why I created my own indicators for project portfolio and want to
remove standard indicators that are useless for us.
Playing with resource availability like other people advised me is not
suitable in my case as I do track resource load and level resource basing on
their actual availability, but only for projects included in project
portfolio.
BR,Elena.
"Mike Glen" пишет: