Hi

I want to use the weekends as regular work time. How can i do this?
The time planned for a task will always expand over the weekend.
 
M

Mike Glen

Hi Udo,

Welcome to this Microsoft Project newsgroup :)

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #7 on setting calendars, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
M

Marlene Villeneuve

Hi Udo,

Go to Tools > Change working time
select your project calender
HIghlight the Sat and Sun column header and enter in the working times on
the left. If you have a 7 day working week you will also need to go to tools
options > scheduling and indicate that there also.
 