actual dates if I have entered them already.
In many other tasks there is no problem. about 20% of my tasks
have this issue. In the other 80% of my tasks, I can enter actual
start and actual finish, and then I can enter actual work and all
the data is input correctly.
BEFORE:
Actual Start of June 5th. Actual FInish=NA
Start=June 5th. Finish= June 16th.
Actual Work = 5 hours.
Remaining work = 35 hours.
Work = 40 hours.
Duration=10 days
% complete = 13% (5/40=13%)
AFTER ENTERING ACTUAL FINISH of June 12th:
Actual Start of June 5th. Actual FInish=June 12th
Start=June 5th. Finish= June 12th.
Actual Work = 12 hours.
Remaining work = 0 hours.
Work = 12 hours.
Duration=6 days
% complete = 100% (12/12=100%)
AFTER UPDATING ACTUAL WORK TO 40 HRS:
Actual Start of June 5th. Actual FInish=June 23rd
Start=June 5th. Finish= June 23rd.
Actual Work = 40 hours.
Remaining work = 0 hours.
Work = 40 hours.
Duration=15 days
% complete = 100% (40/40=100%)
AFTER SETTING ACTUAL FINISH BACK TO June 12th:
Actual Start of June 5th. Actual FInish=June 12th
Start=June 5th. Finish= June 12th.
Actual Work = 12 hours.
Remaining work = 0 hours.
Work = 12 hours.
Duration=6 days
% complete = 100% (12/12=100%)
:
But you said you want the duration not to change when you enter
actual work and remaining work. If we were supposed to be at 50%
work complete today but are instead at 60% and we actually worked
at 100% precisely as assigned, for the scheduled amount of work to
be 60% of the total instead of the 50% we expected, that suggests
that the toal work required has changed. Unless we disconnect
work and duration - ie, disconnect task status from resource
status - that change of total work also implies change of total
duration. You either want changes to work to affect duration or
you don't, you can't have it both ways.
The schedule reflects history for what has taken place and
forecasts for the future based on the consequences of those
historical actuals. For example, if I have task A scheduled for 5
days starting this past Monday linked to task B, task B will show
starting next Monday. But if you input that Task A has had 16
hours of work put in and 16 hours of work to go, that implies that
the real duration SHOULD have been 4 days, not 5. The schedule
will change to reflect that fact, show 50% work complete AND 50%
(duration) complete, reschedule A's finish to tomorrow (Thur)(it
doesn't know whether another 8 hours of actuals will be posted for
Wed so it just assumes it will until you tell it otherwise) and
pulls Task B forward to start Friday instead of Monday. This is
in keeping with Project's role as a dynamic monitoring tool,
keeping you advised on the consequences of actual performance
differing from predicted performance so that you can always keep
the project on track towards the most efficient achievement of its
stated goals.
We might be able to better help you out of this quandry if you can
provide step-by-step exactly how the project looks before posting
updates and exactly step by step how to duplicate the problem.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
The calendar for the project has 5 days of work (M-F) hours are
8-12 & 1-5.
8 hours per day. The resource for the task in question works the
default calendar for June. (although similar effects happen for
tasks assigned to any resource seemingly at random).
Tools-options-calendar shows 8 hours per
day.
I read the help section on the "Updating task status updates
resource status" and I am concerned that this will cause the %
complete to not be updated. Unfortunately, mgmt uses % complete
as an indicator of project status. I cannot have this not get
updated as I enter actual work, remaining
work, actual start, and/or actual finish.
:
Something seems very odd about your calendars I think. What
does the Project calendar say are the working time hours? What
does the resource calendar for the resource assigned to this
task say? On the Tools, Options
menu, Calendar tab, what is the setting for Hours per Day?
To enter actual work without changing duration (and vice versa)
look at the
Calculation tab, the first checkbox "Updating task status updates
resource
status" and turn it off.
What you state is unfortunately not true actual finish and
duration change
as a result of changing actual work and vise-versa.. I enter
actual start
(6/5/2006). Then I enter actual finish (6/12/2006). This
automatically
sets
the actual work to 12 hours. The duration (and I don't care
about duration
particularly) is 6 days. I then change actual work to 40 hrs to
reflect
that
the worker assigned put in 40 hrs over that period. At this
point the actual
finish is 6/23/2006 (I did this last week so somehow it thought
I was predicting the future). The actual duration goes to 15
days. Changing the
actual finish back to 6/12 will adjust the actual duraction
back to 6 days
and the actual work to 12 hrs. The only way I can find to get
40 hrs over
6
dasy is overallocate the resource at 3000%. (NOTE: I did not
do a binary
search to find the minimum allocation, but 200% was too
little.) The resource's calendar allows for 8 hours/day M-F.
Not that it matters since
I
am entering actuals.
:
Hi,
I'm afraid you are somewhat uncklear about what you are doing
here. Once you enter ACTUAL START and ACTUAL FINISH (not just
different values
in
Start and Finish) Project will no longer recalculate them
unless... unless
you tell it to do so by changing ACTUAL DURATION (which is the
working time
between start and finish, by definition.
OTOH, when you enter Actual WORK, dates remain unchanged and
unly units
are
recalculated to match the Work=duration times units equation.
HTH
--
Jan De Messemaeker, Microsoft Project Most Valuable
Professional
http://users.online.be/prom-ade/
For FAQs:
http://www.mvps.org/project/faqs.htm
"MT" <
[email protected]> schreef in bericht
I have tasks in my plan where I cannot enter both actual
hours and actual
start & end dates. Why would this occur? How can I prevent
it, because
it
is really annoying? (MS Project Professional 2003).
For example, on one task I entered the actual start date of
June 5th and
the
actual end date of June 12th. I said it took the resource
assigned to
it
40
hrs (actual hours). The actual end date changed to June
23rd. I changed
the
actual end date back to June 12th and the actual hours
changed to 12 hours. Changing actual hours back to 40 reset
the actual end date to the 23rd.
The resource has a calendar of 5 days of 8 hours of work each
week. No
May
or June vacation. I don't see how this even matters however
since I am
entering ACTUALS and not a schedule.
Entering the actuals changed the resource allocation from
100% to 123%.
I
tried changing to fixed duration, fixed work, and back to
fixed units,
but
got the same behavior. I was able to work around it by
increasing the
allocation of the resource to 3000% (three thousand).