R
Richard Lytle
I am updating my project plan (due to schedule changes and addtional tasks)
and need to relevel my resources. However, I would like to have tasks that
are 100% complete to be ignored during leveling. (In other words, why would
I want schedule a resource's time to work on a completed task?)
Is this possible (without actually deleting completed tasks from my work
plan)?
Thanks in advance for any help!
and need to relevel my resources. However, I would like to have tasks that
are 100% complete to be ignored during leveling. (In other words, why would
I want schedule a resource's time to work on a completed task?)
Is this possible (without actually deleting completed tasks from my work
plan)?
Thanks in advance for any help!