Has anyone ever copied the late dates (start and finish) to the baseline
start and finish dates? If so, please explain to me why one would do this.
Is this the proper way to schedule to the need dates?
start and finish dates? If so, please explain to me why one would do this.
Is this the proper way to schedule to the need dates?