Late Start and Late Finish

C

Cheryl

I have a need to display the red, green, Yellow Stop lights for tasks that
have a late or currently scheduled late start and a late or currently
scheduled late finish. Can I use a function and 2 custom number fields to
accomplish this?

Thanks in advance.
 
C

Cheryl

I am using MS Project 2002 Standard. I need the capability to do the
following:
Display a red stop light for tasks that are scheduled to have started but
have not
Display a yellow stop light for tasks that are schedules to start in the
next 2 days
display a green stop light for task that have started on time or are future
tasks

I want to use the same schema for the late finish

Any help is appreciated.
 
M

Mike Glen

Hi Cheryl,

Welcome to this Microsoft Project newsgroup :)

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #14 & 15 on customizing fields, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the articles before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 