G
Gil
Hi all,
I have 2 problems, and I will appreciate any help:
1)
As an example, assume I have only two assignment: A (50 hours) and B
(20 hours), and both are assigned to the same resource, with no
dependencies or other constraints. Since my resource has the default 8
hours calendar and max units of 100%, he will be over-allocated,
because both tasks are scheduled to the project start date.
After leveling this resource task B is delayed and starts when task A
is finished, and the resource is not over-allocated anymore. So far so
good, but...
Assume that task A is only 8 hours. I change the work field to 8 hours
(all tasks are fixed work type), and duration is shortened to only 1
day, but task B is still far in the future, based on the leveling
delay that was created before, even though now only a leveling delay
of one day is required, and not of 8 days, meaning the tasks do not
start as soon as possible... the solution is to level resources again,
and now the tasks will again start as soon as possible. but if this is
the solution it means that after every change in the plan I need to
level resources again and again to make sure nothing is being delayed
for no reason?!
I guess Automatic leveling can solve this issue, but it is not
recommended at all...
2)
I created two generic resources in the resource sheet. QA (max units
of 30%) and DEV (max units of 200%). Why, when I assign them to tasks,
the default assignment units of QA is 30% (like max units) but the
default assignment units of DEV is 100% (not like max units, which is
300%)? Why do I have to manually change this to 300%? why isn`t the
default assignment units equals max units also when it is above 100%?
Thanks,
Gil
I have 2 problems, and I will appreciate any help:
1)
As an example, assume I have only two assignment: A (50 hours) and B
(20 hours), and both are assigned to the same resource, with no
dependencies or other constraints. Since my resource has the default 8
hours calendar and max units of 100%, he will be over-allocated,
because both tasks are scheduled to the project start date.
After leveling this resource task B is delayed and starts when task A
is finished, and the resource is not over-allocated anymore. So far so
good, but...
Assume that task A is only 8 hours. I change the work field to 8 hours
(all tasks are fixed work type), and duration is shortened to only 1
day, but task B is still far in the future, based on the leveling
delay that was created before, even though now only a leveling delay
of one day is required, and not of 8 days, meaning the tasks do not
start as soon as possible... the solution is to level resources again,
and now the tasks will again start as soon as possible. but if this is
the solution it means that after every change in the plan I need to
level resources again and again to make sure nothing is being delayed
for no reason?!
I guess Automatic leveling can solve this issue, but it is not
recommended at all...
2)
I created two generic resources in the resource sheet. QA (max units
of 30%) and DEV (max units of 200%). Why, when I assign them to tasks,
the default assignment units of QA is 30% (like max units) but the
default assignment units of DEV is 100% (not like max units, which is
300%)? Why do I have to manually change this to 300%? why isn`t the
default assignment units equals max units also when it is above 100%?
Thanks,
Gil