- this example based on an 8 hour day
- T1 and T2 are Task / Assignments
- assign two resources to a couple of tasks at (say) 75% each
- both resources are now overallocated (150%)
- level the schedule (using hour-by-hour, standard levelling order)
- task 2 is delayed by 1 eday (24 elapsed period)
- the resouces are are now only allocated 75%
- the 2nd activity is (e)delayed into the "next" day
1) Before Leveling
Mon Tues
Fred 12h <---- 150% Allocated
T1 6h
T2 6h
Tom 12h
T1 6h
T2 6h
2) After Leveling (withhour by hour option)
Mon Tues
Fred 6h 6h <--- 75% Allocated (25% Underallocated)
T1 6h
T2 6h
Tom 6h 6h
T1 6h
T2 6h
3) Desired state after leveling !!!
Mon Tues
Fred 8h 4h
T1 6h
T2 2h 4h
Tom 6h 4h
T1 6h
T2 2h 4h
Anyone out there done work in this area? Are there MSP add-ins that can
help?
Regards
Doc
Mark "Doc" Dochtermann, PMP, CISSP, MSP Black Belt
(e-mail address removed)
- T1 and T2 are Task / Assignments
- assign two resources to a couple of tasks at (say) 75% each
- both resources are now overallocated (150%)
- level the schedule (using hour-by-hour, standard levelling order)
- task 2 is delayed by 1 eday (24 elapsed period)
- the resouces are are now only allocated 75%
- the 2nd activity is (e)delayed into the "next" day
1) Before Leveling
Mon Tues
Fred 12h <---- 150% Allocated
T1 6h
T2 6h
Tom 12h
T1 6h
T2 6h
2) After Leveling (withhour by hour option)
Mon Tues
Fred 6h 6h <--- 75% Allocated (25% Underallocated)
T1 6h
T2 6h
Tom 6h 6h
T1 6h
T2 6h
3) Desired state after leveling !!!
Mon Tues
Fred 8h 4h
T1 6h
T2 2h 4h
Tom 6h 4h
T1 6h
T2 2h 4h
Anyone out there done work in this area? Are there MSP add-ins that can
help?
Regards
Doc