P
Paul Clements
Hi,
I have a question relating to resource levelling within Project 2003.
Levelling works fin in my project when I only have one resource assigned to
a task.
However, when I have multiple tasks and multiple resources assigned to each
of the tasks I cannot get it to work.
Task 1-6 last 1 day uses resource X and Y.
There are no dependencies between them so if the resources were available
then they could all start on the same day and all complete at the end of the
day.
However, if it was only that simple, there are only 2 X's and 4 Y's so I
expected with my limited knowledge about levelling that I would get a schedule
Task 1 and 2 start day 1 complete day 1
Task 3 and 4 start day 2 complete day 2
Task 5 and 6 start day 3 and complete day 3
However I get the following schedule
Task 1,2,3 and 4 start day 1 complete day 1
Task 5 and 6 start day 2 and complete day 2
I have set each of the tasks to have different priorities, task 1 being the
greatest and task 6 being the lowest. I am levelling on Priority and
Standard. Each of the resources are 100% allocated to the task
I confess I am a project beginner who is trying to demonstrate to a client
the impact of constraints on their resources (people and computers) and
thought it would be possible this way.
I would appreciate any advice on how or if this can be achieved using
Project 2003.
Thanks in advance and happy to provide any clarification.
Paul
I have a question relating to resource levelling within Project 2003.
Levelling works fin in my project when I only have one resource assigned to
a task.
However, when I have multiple tasks and multiple resources assigned to each
of the tasks I cannot get it to work.
Task 1-6 last 1 day uses resource X and Y.
There are no dependencies between them so if the resources were available
then they could all start on the same day and all complete at the end of the
day.
However, if it was only that simple, there are only 2 X's and 4 Y's so I
expected with my limited knowledge about levelling that I would get a schedule
Task 1 and 2 start day 1 complete day 1
Task 3 and 4 start day 2 complete day 2
Task 5 and 6 start day 3 and complete day 3
However I get the following schedule
Task 1,2,3 and 4 start day 1 complete day 1
Task 5 and 6 start day 2 and complete day 2
I have set each of the tasks to have different priorities, task 1 being the
greatest and task 6 being the lowest. I am levelling on Priority and
Standard. Each of the resources are 100% allocated to the task
I confess I am a project beginner who is trying to demonstrate to a client
the impact of constraints on their resources (people and computers) and
thought it would be possible this way.
I would appreciate any advice on how or if this can be achieved using
Project 2003.
Thanks in advance and happy to provide any clarification.
Paul