S
Steve
I have a master project in (MSP7) with 5 inserted subprojects. The master
project has no tasks, its just a container. Four of the subprojects are
deeply detailed with daily information that applies to the stakeowner of that
phase of the program. The fifth subproject is more or less a Summary
project. It reflects key milestones and those viewed as critical tasks
events as an overview.
I have no problem creating an external link such as from one subproject task
as a Start to Start predecessor to a task in Summary subproject. My problem
is I can not bring the Duration information over to feed linked task. MSP7
is not allowing me to do a dynamic link between the duration fields. I have
to manually copy the the durations as they change.
I'm I missing a step or procedure? Or is there a work around?
Thanks,
Steve
project has no tasks, its just a container. Four of the subprojects are
deeply detailed with daily information that applies to the stakeowner of that
phase of the program. The fifth subproject is more or less a Summary
project. It reflects key milestones and those viewed as critical tasks
events as an overview.
I have no problem creating an external link such as from one subproject task
as a Start to Start predecessor to a task in Summary subproject. My problem
is I can not bring the Duration information over to feed linked task. MSP7
is not allowing me to do a dynamic link between the duration fields. I have
to manually copy the the durations as they change.
I'm I missing a step or procedure? Or is there a work around?
Thanks,
Steve