N
Neil
How do I setup a 4on 4off shift pattern in projects
Neil said:How do I setup a 4on 4off shift pattern in projects
Neil said:Thanks for the helpful responce John
The shift pattern I need to use is
Day shift 0600-1800
Night Shift 18-00-0600
The problem that I have is that project only seems to allow shifts that fit
into the 7 day week, I need to use an 8day week (in the words of the famous
song!)
That then gives 24/7 coverage using 4 people (its a very popular shift)
Any ideas much appreicated
Neil
Neil said:Hello John
Thanks for the responce, to expand slightly on what I am trying to achieve;
Shift 1 start 0600am- ends 1800pm
Shift 2 starts 1800pm- ends 0600am(next day)
Shift 1 works 4 days then has 4 days off then works shift 2 for 4 days then
4 days off.
Shift 2 works opposite shift 1.
Sfift 3 and 4 work the same pattern but staggered so as to give 1 person on
duty 24/7
These shift patterns are use by Police, Fire Department, Airport and Airline
Operations, Gas Stations in fact anyservice outside of the normal Mon-Fri.
The important point is that to cover 24/7 it is necessary to think outside
of the working week based on seven days. The rotation in this case being
over a 56day period
There are lots of other rotations that are used ie 7days on duty 3 days off
7 days on 4 days off. (ie work 14days in a 21day period)
The question therefore is "Can Project Handle Shift Patterns that work on a
rotation outside of the 7day week"
Any ideas for this reak world situation would be much appreicated
Neil
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.