C
crook
Hi!
I fielded the following question from a PM today:
"Is there a setting to drive down "Work" rather than driving up "Actual
Work" when marking a task 100% complete?"
This PM would rather have Project keep the actual work entered and
drive remaining work to zero when he uses the Tracking toolbar, rather
than open each task and set remaining work to zero manually. I suppose
I don't blame him. However I found the following from the help files
which suggests that driving remaining work to zero is not possible:
Office Project 2003 calculates the actual work (actual work: The amount
of work that has been performed on a task or assignment. When you enter
actual work on a task, the remaining work is calculated using this
formula: Remaining Work = Work - Actual Work. Actual work is often
referred to as "actuals.") and remaining work (remaining work: The
amount of work, in terms of a time unit such as hours or days, that is
left to be completed on a task. This is calculated as follows:
Remaining Work = Work - Actual Work.) according to the formulas Actual
Work = Work * Percent Work Complete and Remaining Work = Work - Actual
Work."
Is it possible to reverse Project Pro's algorithm to drive remaining
work to zero rather than calculating actual work based on planned work?
Is there such a setting?
Thank you for your time and attention!
Crook
I fielded the following question from a PM today:
"Is there a setting to drive down "Work" rather than driving up "Actual
Work" when marking a task 100% complete?"
This PM would rather have Project keep the actual work entered and
drive remaining work to zero when he uses the Tracking toolbar, rather
than open each task and set remaining work to zero manually. I suppose
I don't blame him. However I found the following from the help files
which suggests that driving remaining work to zero is not possible:
"When you specify the percentage of work complete for a task, MicrosoftFrom the help topic: Update the percentage of work complete
Office Project 2003 calculates the actual work (actual work: The amount
of work that has been performed on a task or assignment. When you enter
actual work on a task, the remaining work is calculated using this
formula: Remaining Work = Work - Actual Work. Actual work is often
referred to as "actuals.") and remaining work (remaining work: The
amount of work, in terms of a time unit such as hours or days, that is
left to be completed on a task. This is calculated as follows:
Remaining Work = Work - Actual Work.) according to the formulas Actual
Work = Work * Percent Work Complete and Remaining Work = Work - Actual
Work."
Is it possible to reverse Project Pro's algorithm to drive remaining
work to zero rather than calculating actual work based on planned work?
Is there such a setting?
Thank you for your time and attention!
Crook