P
ProjectHelp
I have a question regarding Microsoft Project linking between multiple
project plans. Currently my process is to link each of my workstream project
plan milestones into a "Consolidated Milestone" view. So I've copied certain
tasks (and their start, resource name, duration columns, etc columms) and do
a "paste special" then "paste link" then "text data" into the target
consolidated file. This creates the normal shadded arrow in the corner of
each linked cell.
Now I noticed with 3 of my 7 workstream project plans, that when I opened my
consolidated view project plan and re-established the links, that certain
fields were not represented the way there were in their specific workstream
plan. For instance, one task had 5 days for duration and an finish date of
11/17. However it appears the Consolidated view "reconciled" that new
duration/date and change it to 2.5 days and and moved up the finish date to
11/14.
I'm wondering why the "linked URL tasks" didn't just appear as they were
pulled from the indivudal workplans. Is there anything I can do to just have
the Consolidated Project plan accept whatever the values in from the
workstream plans present? Is there another way to link these plans? Also,
does it matter if the individual workstream filenames contain spaces or
characters such as (- or _) that might break the URL links?
Thanks in advance.
project plans. Currently my process is to link each of my workstream project
plan milestones into a "Consolidated Milestone" view. So I've copied certain
tasks (and their start, resource name, duration columns, etc columms) and do
a "paste special" then "paste link" then "text data" into the target
consolidated file. This creates the normal shadded arrow in the corner of
each linked cell.
Now I noticed with 3 of my 7 workstream project plans, that when I opened my
consolidated view project plan and re-established the links, that certain
fields were not represented the way there were in their specific workstream
plan. For instance, one task had 5 days for duration and an finish date of
11/17. However it appears the Consolidated view "reconciled" that new
duration/date and change it to 2.5 days and and moved up the finish date to
11/14.
I'm wondering why the "linked URL tasks" didn't just appear as they were
pulled from the indivudal workplans. Is there anything I can do to just have
the Consolidated Project plan accept whatever the values in from the
workstream plans present? Is there another way to link these plans? Also,
does it matter if the individual workstream filenames contain spaces or
characters such as (- or _) that might break the URL links?
Thanks in advance.