Here's the scenario:
Milestone is task 100 - ends Oct. 28
Task 123 is a subtask of 122
Task 123 has Milestone 100 as predecessor, FS Type, lag time 0
Why doesn't the date for task 123 start after the milestone?
If I outdent task 123 to same level as the milestone, the start date is
correct as 10/31
If I leave it as a subtask of 122, it uses task 122 end date.