Milestone Tasks and their successors

E

Elaine

Hello

I have a Milestone Task with a date Wednesday 04/02/04.
Its successors have start dates Thursday 05/02/04.

On my colleague's High Level Schedule - from where these
activities have been manually copied - the successor tasks
both have start dates of Wednesday 04/02/04...which is
what I want mine to show.

Sorry - but I can't for the life of me find the option
that tells milestones not to push successor tasks to the
next day.

Hope you can help. Thanks very much

Elaine.
 