Milestones

V

Verossa

Hi All

I define milestone and then link a task to it. Why do some tasks start on the same date as the milestone and other tasks start on the following day?

Is there some setting I have activated.

TIA to all who respond,
Vers
 
G

Gérard Ducouret

Hello Vers,
If the milestone as a Must Start On constraint (8:00 AM) the following task
will start the same day.
If the milestone as a Must Finish On constraint (17:00 AM) the following
task will start the folowing day.

Hope this helps,

Gérard Ducouret

Verossa said:
Hi All

I define milestone and then link a task to it. Why do some tasks start on
the same date as the milestone and other tasks start on the following day?
 
R

RMcFarron

What if the milestone has no contraint? I still get the some start on the same day some start the day after

TIA!
 
G

Gérard Ducouret

Display the time in the Start and Finish fields : Tools / Options / View /
Date Format : .12:33

If the milestone is positioned at 8:00, the following task will follow the
same day.

If it is at 17:00, the task will follow the following day.



Gérard Ducouret



RMcFarron said:
What if the milestone has no contraint? I still get the some start on the
same day some start the day after.
 
V

verossa

Hi Gerard,

Thanks for the clarification - I'll take a look at the constraints.

Cheers - Vers
 