J
Jorge
I'm building a master project schedule from different mpp files. In
each mpp I created a custom fields set including numbers, dates and
custom outline code fields. I want to create external dependencies
between my master project and some milestones in my sub-projects. When
I created the cross-link between projects through the New Window, I
also copy my custom field definition to the new window, IOW the 3
project have the custom field definition before I created the cross-
link. The result is that my external dependency from sub-projects show
the standard fields in the master project (% completion, finish date
etc.) and any update on sub-projects is replicated in the master
project but the value of the custom fields are missing. I tried doing
a field external link with the same result with the outline code
fields but the date custom field works. Could someone give me some
advice about how solve this situation. Thanks.
each mpp I created a custom fields set including numbers, dates and
custom outline code fields. I want to create external dependencies
between my master project and some milestones in my sub-projects. When
I created the cross-link between projects through the New Window, I
also copy my custom field definition to the new window, IOW the 3
project have the custom field definition before I created the cross-
link. The result is that my external dependency from sub-projects show
the standard fields in the master project (% completion, finish date
etc.) and any update on sub-projects is replicated in the master
project but the value of the custom fields are missing. I tried doing
a field external link with the same result with the outline code
fields but the date custom field works. Could someone give me some
advice about how solve this situation. Thanks.