Ms Project 2007 Baseline Cost problem

Ö

Özgür ÖZTÜRK

Hi,
I have got a problem at Ms Project 2007. I create a consturaction project
and there was 400+ task in it. My project's baseline cost = 30.036.049,94 $.
When i click reports, costs; cash flow i see the cash flow report. But at
cash flow report baseline cost = 30.027.081.83 $. Why these baseline costs
are not equal ? How can i fix this problem ?

Thanks.

Ozgur OZTURK
System Engineer (MCT, MCSE-S)
 
J

JulieS

Hello Ozgur,

I am not able to see the problem you report. A quick question, the cash
flow report accessible through Report > Reports, is not baseline cost
data, it's cost data. Did you modify the default report to show
baseline cost instead of cost?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top