MS Project how change the duration field display from days to d

S

Shreck

In MS Project, how can I change the duration field display from "days" to "d"?

e.g. I want the Gantt Chart Duration column to display "3 d" instead of "3
days"

I am using -
MS Office Project Professional 2003
MS Windows XP Professional SP 2
 
J

JulieS

Hi Shreck,

Tools > Options, Edit tab. Set the "View Options" for days to "d".
Click the Set as Default button to apply to all Project files created
from that point forward. Project files you have already created you'll
need to change one at a time.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top